Dorchester Hotel v Vivid Interiors: Court Intervention
January 2009
The Dorchester Hotel had engaged Vivid Interiors, under a JCT standard form contract to carry out the refurbishment of its hotel. Vivid completed the works in September 2007 and submitted a draft final account around the end of March 2008. On 19 December 2008, just before the Christmas holiday, Vivid Interiors referred its final account to adjudication. The Referral, which was some 92 pages, was accompanied by 37 lever arch files, including new files containing six detailed witness statements and two experts' reports. Many of the figures had been modified, albeit by a small amount, from the March submission.
An adjudicator was appointed but he advised that a condition of his appointment was that the Christmas holiday period would not be included in the 28-day adjudication period. Vivid agreed to this so that the date for the adjudicator’s decision became 28 January 2009. Although the adjudicator believed this to be sufficient, Vivid agreed to extend the period for the Dorchester’s response so that it had until 28 January 2009 and the adjudicator was to reach his decision by 28 February 2009.
The Dorchester maintained throughout that the timetable was extremely tight and it was very likely that there could be a breach of natural justice if it was forced to respond in the time available. The Dorchester therefore commenced Part 8 proceedings to seek declaratory relief to the effect that “there is a serious risk of a breach of natural justice in the conduct of the adjudication … and, unless the parties agree a realistic timetable …, any decision issued by the adjudicator against the existing timetable … would be unenforceable by reason of breach of natural justice”.
The matter was brought before Mr Justice Coulson who decided that he did have jurisdiction to consider applications for declaratory relief in such circumstances. However, on the facts of this case he declined to give the relief sought on 4 separate grounds:
- The adjudicator had made it clear that he could determine the adjudication by 28 January 2009 or indeed the extended date. In line with CIB vs Birse [2005], it was up to the adjudicator to decide whether he was able to reach a fair timetable in the time available.
- He did not believe that the timetable in this case was incapable of giving rise to a fair result.
- Mr Justice Coulson did not consider that he was not in a position to be able to say whether or not the new material would lead to a breach of natural justice.
- Even if the declarations were refused, the Dorchester would not be left without a remedy. It would still be open to them to resist enforcement proceedings at a later stage.
This case underlines the position that only in the rarest of cases will the courts intervene in an ongoing adjudication. It is interesting to note that Mr Justice Coulson thought that the situation in CJP Builders Ltd vs William Verry Ltd [2008] would have warranted such an intervention.
The full judgement can be downloaded here.
Dorchester Hotel Ltd v Vivid Interiors Ltd [2009] EWHC 70 (TCC)
This article contains information on current legal issues but is for information purposes only. It should not be relied upon or be construed as advice or applied to any particular set of facts. If you have a particular issue please take professional advice.
Legal News
Jan 2010 | Testimony to the Importance of the Expert Witness
Oct 2009 | Goodbye to the Law Lords
May 2009 | Construction Act Reforms - Never Ending Story ... Part II
Jan 2009 | Dorchester Hotel v Vivid Interiors: Court Intervention
Jan 2009 | OSC Building Services v Interior Dimensions Contracts: Interim or Final
Nov 2008 | Serial Drama: Benfield Construction v Trudson (Hatton)
Oct 2008 | One Cherry - One Bite: Birmingham City Council v Paddison Construction Limited
Sep 2008 | Do you have a dispute? More than likely - yes
Sep 2008 | Letters of Intent: A Salutary Warning
Aug 2008 | Breach of Natural Justice - CJP Builders v William Verry
Jul 2008 | Adjudicator's Bias - Makers UK Ltd v London Borough of Camden
Jul 2008 | Adjudication July 2008
Jun 2008 | Enforcing expert's decisions: Owen Pell Ltd v Bindi (London) Ltd
Jun 2008 | Civil Justice Council encourages early ADR
Jun 2008 | Beware the 'Battle of the Forms'
May 2008 | New Protection for Consumers
May 2008 | Gordon Brown confirms Construction Act will be amended